Is a battery load test required in Ontario?

Short answer

The Ontario Fire Code does not mention batteries in its fire alarm testing article. It requires testing in conformance with CAN/ULC-S536, 2019 edition from 1 January 2026. Supplier guidance published through OECM says that means a load test with recorded results in place of a voltage check.

Edition: CAN/ULC-S536-2019Updated 2026-11-22Source: OECM and EPI Fire Protection: battery load testing requirements

What does the Fire Code say?

Sentence 6.3.2.2.(1) of the Ontario Fire Code requires a fire alarm system to be inspected and tested in conformance with CAN/ULC-S536. Table 1.2.1.A names the 2019 edition. How a battery is tested is set by the standard, not by the Code.

What do suppliers say changed?

EPI Fire Protection's update, published by OECM, describes the change as “the shift from simple voltage checks to mandatory true battery load testing”. It adds that load-test results go in the documentation as numbers.

That update names a 2024 edition of the standard. The Fire Code's table names 2019. Tap Report's summary of the 2019 edition also lists new battery tests.

What should the record show?

The standard sets the required values. As a working rule, record enough for someone else to check the result:

  • Battery make, model and rated capacity.
  • The voltage before the test.
  • The load applied and for how long.
  • The voltage under load.
  • The result, the date and time, and who did the test.

The free report template has a line for each.

Is sizing the same as testing?

No. Sizing works out the capacity a panel needs, before a battery is chosen. Testing measures the battery that is installed. For sizing, use the battery standby calculator.

Sources

Read on 2026-11-22. This page is a summary, not legal advice. The Fire Code and the standard govern.

Questions

Is a voltage reading enough?
Supplier guidance published through OECM says no: from 1 January 2026 batteries are tested under load and the results are recorded.
Where does the result go?
In the power supply section of the inspection report, with the measured values.
Does the Fire Code state the pass value?
No. The Fire Code refers to CAN/ULC-S536. The values are in the standard.